2023 Church Street Sanitary Replacement

Share 2023 Church Street Sanitary Replacement on Facebook Share 2023 Church Street Sanitary Replacement on Twitter Share 2023 Church Street Sanitary Replacement on Linkedin Email 2023 Church Street Sanitary Replacement link
Church street Sanitary Replacement Project 2023

The Town of Pelham is upgrading the existing sanitary infrastructure to improve the capacity on Church Street between Canboro Road to Foss Road.

This project upgrade will allow all the future development happening in Fenwick to connect to the sanitary network and minimize the risk to existing homeowners. This sanitary sewer replacement of approximately 1.03 kilometres will include the replacement of the existing infrastructure and will improve the overall efficiency of the sanitary system.

Construction is scheduled to begin July 4th, 2023, and has an anticipated completion for the Fall of 2023. Project updates and details on the stage of the project will be updated in the Project Timeline.

The project will include the reconnection of sanitary lateral and a significant crossing of CP Rail. In order to protect construction workers and complete the work safely and cost-effectively, a traffic closure is required at the CP rail line during trenchless operations.

Church Street will be open for local traffic only, providing residents and visitors to the park access during construction.

This contract will be carried out for the Town by Trenchline and Roads. The contract administrator for the project, who will also carry out full-time project inspection on behalf of the Town, is Associated Engineering.


The Town of Pelham is upgrading the existing sanitary infrastructure to improve the capacity on Church Street between Canboro Road to Foss Road.

This project upgrade will allow all the future development happening in Fenwick to connect to the sanitary network and minimize the risk to existing homeowners. This sanitary sewer replacement of approximately 1.03 kilometres will include the replacement of the existing infrastructure and will improve the overall efficiency of the sanitary system.

Construction is scheduled to begin July 4th, 2023, and has an anticipated completion for the Fall of 2023. Project updates and details on the stage of the project will be updated in the Project Timeline.

The project will include the reconnection of sanitary lateral and a significant crossing of CP Rail. In order to protect construction workers and complete the work safely and cost-effectively, a traffic closure is required at the CP rail line during trenchless operations.

Church Street will be open for local traffic only, providing residents and visitors to the park access during construction.

This contract will be carried out for the Town by Trenchline and Roads. The contract administrator for the project, who will also carry out full-time project inspection on behalf of the Town, is Associated Engineering.


  • Church Street at Canboro Road - Three-Week Closure Anticipated

    Share Church Street at Canboro Road - Three-Week Closure Anticipated on Facebook Share Church Street at Canboro Road - Three-Week Closure Anticipated on Twitter Share Church Street at Canboro Road - Three-Week Closure Anticipated on Linkedin Email Church Street at Canboro Road - Three-Week Closure Anticipated link

    The area of Church Street and Canboro Road will be closed beginning September 25th, 2023.

    Residents in the area have been notified by mail of the closure, which is anticipated to be closed for an anticipated three weeks.


  • Church Street Project experiences timeline delay

    Share Church Street Project experiences timeline delay on Facebook Share Church Street Project experiences timeline delay on Twitter Share Church Street Project experiences timeline delay on Linkedin Email Church Street Project experiences timeline delay link
    supporting image

    The road closure will continue for an additional six weeks due to a timeline delay. The project completion is anticipated to be done during the fall of 2023.

    See attached detour plan for the closure.

    The contractor is required to provide safe pedestrian access at all times; please use care if pedestrians are required to walk through the construction zone.

  • Road Closure Notification

    Share Road Closure Notification on Facebook Share Road Closure Notification on Twitter Share Road Closure Notification on Linkedin Email Road Closure Notification link
    supporting image

    In order to protect construction workers and complete the work safely and cost-effectively, a traffic closure is required at the CP rail line during trenchless operations.

    The Road closure will commence on July 4, 2023, with an anticipated minimum closure of 4 weeks. See attached detour plan for the closure. The contractor is required to provide safe pedestrian access at all times, please use care if pedestrians are required to walk through the construction zone.

Page last updated: 22 Sep 2023, 01:28 PM